Nevada Revised Statutes 278.145 - Report of location of utility project
|
|
Current as of: 2009
1. Each public utility which owns an interest in or is engaged in the construction or operation of a utility project, or on whose behalf the utility project is constructed, which is located in a region or county whose population is 100,000 or more shall, within 60 days after the utility project has been approved for construction, report the location of the utility project to the planning commission of each city, county or region in which it is located. 2. The planning commission of each city, county or region shall maintain a record of each report it receives from a public utility pursuant to subsection 1. ________________________________________________________________________