Connecticut General Statutes 22a-6q – Alternative time frame for action on permit
Current as of: 2023 | Check for updates
|
Other versions
When the commissioner determines, based on the size, novelty, complexity or technical difficulty of a project, that work cannot be completed within the schedule for timely action applicable to a permit application pursuant to subdivision (3) of subsection (b) of § 22a-6p, the commissioner shall notify the applicant of such determination within thirty days of receiving the permit application and shall, within forty-five days of providing such notice, establish an alternative permit schedule for timely action.
Terms Used In Connecticut General Statutes 22a-6q
- commissioner: means the Commissioner of Energy and Environmental Protection or his or her designated agent. See Connecticut General Statutes 22a-2