10. a. A casino licensee or the authority, as appropriate, shall submit a proposed district project plan for approval by the authority under the incentive program.

b. A proposed district project plan submitted under subsection a. of this section shall include, but not necessarily be limited to:

(1) A description of the proposed district project;

(2) An estimate of the total project costs and an estimate of the annual amounts of district project grants anticipated under the incentive program for the casino licensee or the authority;

(3) A statement of any other revenue sources to be used to finance the development of a district project;

(4) A statement of the time needed to complete a district project; and

(5) A statement of the impact that the proposed district project is expected to have on the city of Atlantic City.

L.2001,c.221,s.10.