1.  If a subcontractor and another subcontractor or supplier enter into a subcontract for a public work, the subcontractor may withhold as retainage not more than 5 percent from the amount of any progress payment due under a subcontract which is made before 50 percent of the work has been completed under the subcontract.

Ask a legal question, get an answer ASAP!
Click here to chat with a lawyer about your rights.

Terms Used In Nevada Revised Statutes 338.595

  • Contractor: means :

    (a) A person who is licensed pursuant to the provisions of chapter 624 of NRS. See Nevada Revised Statutes 338.010

  • Public work: means any project for the new construction, repair or reconstruction of a project financed in whole or in part from public money for:

    (a) Public buildings;

    (b) Jails and prisons;

    (c) Public roads;

    (d) Public highways;

    (e) Public streets and alleys;

    (f) Public utilities;

    (g) Publicly owned water mains and sewers;

    (h) Public parks and playgrounds;

    (i) Public convention facilities which are financed at least in part with public money; and

    (j) All other publicly owned works and property. See Nevada Revised Statutes 338.010

  • Subcontract: means a written contract entered into between:

    (a) A contractor and a subcontractor or supplier; or

    (b) A subcontractor and another subcontractor or supplier, for the provision of labor, materials, equipment or supplies for a construction project. See Nevada Revised Statutes 338.010

  • Subcontractor: means a person who:

    (a) Is licensed pursuant to the provisions of chapter 624 of NRS or performs such work that the person is not required to be licensed pursuant to chapter 624 of NRS; and

    (b) Contracts with a contractor, another subcontractor or a supplier to provide labor, materials or services for a construction project. See Nevada Revised Statutes 338.010

  • Supplier: means a person who provides materials, equipment or supplies for a construction project. See Nevada Revised Statutes 338.010

2.  After 50 percent of the work required by the subcontractor or supplier has been performed, the subcontractor shall pay any additional progress payments due under the subcontract without withholding any additional retainage if, in the opinion of the subcontractor, satisfactory progress is being made in the work under the subcontract. The payment must be equal to that paid by the contractor to the subcontractor for the work performed or supplies provided by his or her subcontractor or supplier. If the subcontractor continues to withhold retainage from remaining progress payments:

(a) If the subcontractor does not withhold any amount pursuant to NRS 338.600:

(1) The subcontractor may not withhold more than 2.5 percent of the amount of any progress payment; and

(2) Before withholding any amount pursuant to subparagraph (1), the subcontractor must pay to the subcontractor or supplier 50 percent of the amount of any retainage that was withheld from progress payments pursuant to subsection 1; or

(b) If the subcontractor withholds any amount pursuant to NRS 338.600:

(1) The subcontractor may not withhold more than 5 percent of the amount of any progress payment; and

(2) The subcontractor may continue to retain the amount of any retainage that was withheld from progress payments pursuant to subsection 1.

3.  If the subcontractor receives a payment of interest earned on the retainage or an amount withheld from a progress payment, the subcontractor shall, within 10 days after receiving the money, pay to each of his or her subcontractors or suppliers that portion of the interest received from the contractor which is attributable to the retainage or amount withheld from a progress payment by the subcontractor to his or her subcontractor or supplier.

4.  If, pursuant to subsection 4 of NRS 338.555, the contractor pays to the subcontractor the portion of any retainage withheld by the contractor pursuant to NRS 338.555 for the portion of the work which has been performed by the subcontractor, the subcontractor must pay to the subcontractor’s subcontractors and suppliers the portion of any retainage withheld by the subcontractor pursuant to this section for the portion of the work.