(1) Proceedings for the enforcement of a construction lien and the foreclosure of any interests subject to the construction lien shall not be brought later than 1 year after the date the claim of lien was recorded.
  (2) At the time of commencing an action for the enforcement of a construction lien through foreclosure, the plaintiff shall record a notice of lis pendens with respect to the action in the office of the register of deeds for the county in which the real property involved in the action is located.

Need help reviewing a real estate contract?
Have it reviewed by a lawyer, get answers to your questions and move forward with confidence.
Connect with a lawyer now

Terms Used In Michigan Laws 570.1117

  • Complaint: A written statement by the plaintiff stating the wrongs allegedly committed by the defendant.
  • Contract: A legal written agreement that becomes binding when signed.
  • Counterclaim: A claim that a defendant makes against a plaintiff.
  • Foreclosure: A legal process in which property that is collateral or security for a loan may be sold to help repay the loan when the loan is in default. Source: OCC
  • Lien: A claim against real or personal property in satisfaction of a debt.
  • person: may extend and be applied to bodies politic and corporate, as well as to individuals. See Michigan Laws 8.3l
  • Plaintiff: The person who files the complaint in a civil lawsuit.
  • Real property: Land, and all immovable fixtures erected on, growing on, or affixed to the land.
  (3) As provided in section 111(6), an action to foreclose on a construction lien may be maintained by an agent appointed to represent laborers.
  (4) Each person who, at the time of filing the action, has an interest in the real property involved in the action which would be divested or otherwise impaired by the foreclosure of the lien, shall be made a party to the action.
  (5) In connection with an action for foreclosure of a construction lien, the lien claimant also may maintain an action on any contract from which the lien arose.
  (6) Except as otherwise provided in subsection (1), a lien claimant who has been made a party to an action for foreclosure of a construction lien may enforce his or her own construction lien in the action by a cross-claim or counterclaim, and the owner or lessee may timely join other or potential lien claimants in the action.
  (7) In an action brought by a contractor or subcontractor to enforce a construction lien through foreclosure, the complaint, cross-claim, or counterclaim must show that the owner or lessee was provided a sworn statement, if a sworn statement was requested or required, pursuant to section 110.