1.  To be eligible to provide labor, materials or equipment on a public work, the contract for which a public body has entered into with a construction manager at risk pursuant to NRS 338.1696, a subcontractor must be:

Terms Used In Nevada Revised Statutes 338.16991

  • Authorized representative: means a person designated by a public body to be responsible for the development, solicitation, award or administration of contracts for public works pursuant to this chapter. See Nevada Revised Statutes 338.010
  • Contract: means a written contract entered into between a contractor and a public body for the provision of labor, materials, equipment or supplies for a public work. See Nevada Revised Statutes 338.010
  • Contract: A legal written agreement that becomes binding when signed.
  • person: means a natural person, any form of business or social organization and any other nongovernmental legal entity including, but not limited to, a corporation, partnership, association, trust or unincorporated organization. See Nevada Revised Statutes 0.039
  • Public body: means the State, county, city, town, school district or any public agency of this State or its political subdivisions sponsoring or financing a public work. See Nevada Revised Statutes 338.010
  • Public work: means any project for the new construction, repair or reconstruction of a project financed in whole or in part from public money for:

    (a) Public buildings;

    (b) Jails and prisons;

    (c) Public roads;

    (d) Public highways;

    (e) Public streets and alleys;

    (f) Public utilities;

    (g) Publicly owned water mains and sewers;

    (h) Public parks and playgrounds;

    (i) Public convention facilities which are financed at least in part with public money; and

    (j) All other publicly owned works and property. See Nevada Revised Statutes 338.010

  • Subcontractor: means a person who:

    (a) Is licensed pursuant to the provisions of chapter 624 of NRS or performs such work that the person is not required to be licensed pursuant to chapter 624 of NRS; and

    (b) Contracts with a contractor, another subcontractor or a supplier to provide labor, materials or services for a construction project. See Nevada Revised Statutes 338.010

(a) Licensed pursuant to chapter 624 of NRS; and

(b) Qualified pursuant to the provisions of this section to submit a proposal for the provision of labor, materials or equipment on a public work.

2.  Subject to the provisions of subsections 3, 4 and 5, the construction manager at risk shall determine whether an applicant is qualified to submit a proposal for the provision of labor, materials or equipment on the public work for the purposes of paragraph (b) of subsection 1.

3.  Not earlier than 30 days after a construction manager at risk has been selected pursuant to NRS 338.1693 and not later than 10 working days before the date by which an application must be submitted, the construction manager at risk shall advertise for applications from subcontractors in the manner set forth in paragraph (a) of subsection 1 of NRS 338.1385. The construction manager at risk may accept an application from a subcontractor before advertising for applications pursuant to this subsection.

4.  The criteria to be used by the construction manager at risk when determining whether an applicant is qualified to submit a proposal for the provision of labor, materials or equipment must include, and must be limited to:

(a) The monetary limit placed on the license of the applicant by the State Contractors’ Board pursuant to NRS 624.220;

(b) The financial ability of the applicant to provide the labor, materials or equipment required on the public work;

(c) Whether the applicant has the ability to obtain the necessary bonding for the work required by the public body;

(d) The safety programs established and the safety records accumulated by the applicant;

(e) Whether the applicant has breached any contracts with a public body or person in this State or any other state during the 5 years immediately preceding the application;

(f) Whether the applicant has been disciplined or fined by the State Contractors’ Board or another state or federal agency for conduct that relates to the ability of the applicant to perform the public work;

(g) The performance history of the applicant concerning other recent, similar public or private contracts, if any, completed by the applicant in Nevada;

(h) The principal personnel of the applicant;

(i) Whether the applicant has been disqualified from the award of any contract pursuant to NRS 338.017 or 338.13895; and

(j) The truthfulness and completeness of the application.

5.  The public body or its authorized representative shall ensure that each determination made pursuant to subsection 2 is made subject to the provisions of subsection 4.

6.  The construction manager at risk shall notify each applicant and the public body in writing of a determination made pursuant to subsection 2.

7.  A determination made pursuant to subsection 2 that an applicant is not qualified may be appealed pursuant to NRS 338.1381 to the public body with whom the construction manager at risk has entered into a contract for the construction of the public work.