A. During the construction or modification of any shaft or slope mine, the person engaged in the actual construction or modification of such mine shall employ one or more top persons certified pursuant to § 45.2-534. It is the duty of such top person to examine for proper and safe practices and materials used during the construction or modification of a shaft or slope mine. Such duties shall at all times be performed in the immediate vicinity of the shaft or slope under construction.

Ask a business law question, get an answer ASAP!
Thousands of highly rated, verified business lawyers.
Click here to chat with a lawyer about your rights.

Terms Used In Virginia Code 45.2-704

  • Chief: means the Chief of the Division of Mines of the Department of Energy. See Virginia Code 45.2-100
  • Includes: means includes, but not limited to. See Virginia Code 1-218
  • Person: includes any individual, corporation, partnership, association, cooperative, limited liability company, trust, joint venture, government, political subdivision, or any other legal or commercial entity and any successor, representative, agent, agency, or instrumentality thereof. See Virginia Code 1-230

B. Prior to commencing the excavation of any shaft or slope, the operator shall submit to the Department a copy of the plan that includes the following: (i) the name and location of the mine and shaft or slope; (ii) a description of the work and methods to be used in the construction of the shaft or slope; (iii) a description of the methods to be used to ensure wall and roof stability; (iv) a description of the system of ventilation to be used, including procedures for evacuation of the shaft or slope if a fan stoppage occurs; (v) details of hoisting equipment to be used; and (vi) such other information as the Chief requires. The excavation of such shaft or slope shall not begin until the plan is approved by the Chief.

1980, c. 442, § 45.1-20.1; 1994, c. 28, § 45.1-161.250; 2011, cc. 826, 862; 2021, Sp. Sess. I, c. 387.