(1) The following project delivery methods are authorized for procurements relating to infrastructure facilities:

(a) design-bid-build;

(b) construction management at-risk;

(c) operations and maintenance;

(d) design-build;

(e) design-build-operate-maintain; and

(f) design-build-finance-operate-maintain.

(2) In addition to those methods identified in item (1), the board, by regulation, and the State Engineer, in accordance with § 11-35-3010, may:

(a) approve as an alternate project delivery method any combination of design, construction, finance, and services for operations and maintenance of an infrastructure facility; and

(b) allow or require the governmental body to follow any of the additional procedures established by § 11-35-3024.

(3) Participation in a report or study that is later used in the preparation of design requirements for a project does not disqualify a firm from participating as a member of a proposing team in a construction management at-risk, design-build, design-build-operate-maintain, or design-build-finance-operate-maintain procurement unless the participation provides the business with a substantial competitive advantage. In the Manual for Planning and Execution of State Permanent Improvements, the State Engineer may establish guidance for the application of this item by governmental bodies.