Iowa Code 572.12 – Time of filing against railway
Current as of: 2024 | Check for updates
|
Other versions
Terms Used In Iowa Code 572.12
- Lien: A claim against real or personal property in satisfaction of a debt.
- month: means a calendar month, and the word "year" and the abbreviation "A. See Iowa Code 4.1
572.12 Time of filing against railway.
Where a lien is claimed upon a railway, the subcontractor shall have ninety days from the
last day of the month in which such labor was done or material furnished within which to file the claim therefor.
[R60, §1851; C73, §2137; C97, §3092; C24, 27, 31, 35, 39, §10281; C46, 50, 54, 58, 62, 66, 71,
73, 75, 77, 79, 81, §572.12]
87 Acts, ch 79, §4
Where a lien is claimed upon a railway, the subcontractor shall have ninety days from the
last day of the month in which such labor was done or material furnished within which to file the claim therefor.
[R60, §1851; C73, §2137; C97, §3092; C24, 27, 31, 35, 39, §10281; C46, 50, 54, 58, 62, 66, 71,
73, 75, 77, 79, 81, §572.12]
87 Acts, ch 79, §4