(a) In General.—Before any Federal agency undertakes the construction of a dam, or issues a license to any private individual or corporation for the construction of a dam, it shall give written notice to the Secretary setting forth the site of the proposed dam and the approximate area to be flooded and otherwise changed if construction is undertaken.

Terms Used In 54 USC 312505

  • Corporation: A legal entity owned by the holders of shares of stock that have been issued, and that can own, receive, and transfer property, and carry on business in its own name.
  • Evidence: Information presented in testimony or in documents that is used to persuade the fact finder (judge or jury) to decide the case for one side or the other.
  • individual: shall include every infant member of the species homo sapiens who is born alive at any stage of development. See 1 USC 8

(b) Dams With Certain Detention Capacity or Reservoir.—With respect to any flood water retarding dam that provides fewer than 5,000 acre-feet of detention capacity, and with respect to any other type of dam that creates a reservoir of fewer than 40 surface acres, this section shall apply only when the constructing agency, in its preliminary surveys, finds or is presented with evidence that historical or archeological materials exist or may be present in the proposed reservoir area.