Terms Used In Hawaii Revised Statutes 269-104

  • Contract: A legal written agreement that becomes binding when signed.
  • Net energy metering: means measuring the difference between the electricity supplied through the electric grid and the electricity generated by an eligible customer-generator and fed back to the electric grid over a monthly billing period; provided that:

    (1) Net energy metering shall be accomplished using a single meter capable of registering the flow of electricity in two directions;

    (2) An additional meter or meters to monitor the flow of electricity in each direction may be installed with the consent of the customer-generator, at the expense of the electric utility, and the additional metering shall be used only to provide the information necessary to accurately bill or credit the customer-generator, or to collect solar, wind turbine, biomass, or hydroelectric energy generating system performance information for research purposes;

    (3) If the existing electrical meter of an eligible customer-generator is not capable of measuring the flow of electricity in two directions, the electric utility shall be responsible for all expenses involved in purchasing and installing a meter that is able to measure electricity flow in two directions;

    (4) If an additional meter or meters are installed, the net energy metering calculation shall yield a result identical to that of a single meter; and

    (5) An eligible customer-generator who already owns an existing solar, wind turbine, biomass, or hydroelectric energy generating facility, or a hybrid system consisting of two or more of these facilities, is eligible to receive net energy metering service in accordance with this part. See Hawaii Revised Statutes 269-101

Notwithstanding section contract or tariff; rate structure” class=”unlinked-ref” datatype=”S” sessionyear=”2019″ statecd=”HI”>269-102, an electric utility is not obligated to provide net energy metering to additional customer-generators in its service area when the combined total peak generating capacity of all eligible customer-generators served by all the electric utilities in that service area furnishing net energy metering to eligible customer-generators equals .5 per cent of the system peak demand of those electric utilities; provided that the public utilities commission may increase, by rule or order, the allowable percentage of the electric utility’s system peak demand produced from eligible customer-generators in the electric utility’s service area, whereupon the electric utility will be obligated to provide net energy metering to additional eligible customer-generators in that service area up to the increased percentage amount.