(a) The existing capacity and future needs component shall identify existing and future facilities needed by the county for solid waste management.

Terms Used In Hawaii Revised Statutes 342G-27

  • Bioconversion: means the processing of the organic fraction of the waste stream through biological or chemical means to perform composting or generate products including, but not limited to, fertilizers, feeds, methane, alcohols, tars, and other products. See Hawaii Revised Statutes 342G-1
  • county: includes the city and county of Honolulu. See Hawaii Revised Statutes 1-22
  • Disposal: means the management of solid waste through incineration or landfilling at permitted solid waste facilities. See Hawaii Revised Statutes 342G-1
  • Enterprise zone: means an area selected by a county and approved by the governor to be eligible for the enterprise zone program established under chapter 209E. See Hawaii Revised Statutes 342G-1
  • Recycling: means the collection, separation, recovery, and sale or reuse of secondary resources that would otherwise be disposed of as municipal solid waste, and is an integral part of a manufacturing process aimed at producing a marketable product made of postconsumer material. See Hawaii Revised Statutes 342G-1
  • Solid waste management: means the entire process, or any part thereof, of storage, collection, transportation, transfer, processing, and disposal of solid wastes by any person engaging in these processes. See Hawaii Revised Statutes 342G-1
  • Source reduction: means the design, manufacture, and use of materials to:

    (1) Minimize the quantity or toxicity, or both, of the waste produced; and

    (2) Reduce the creation of waste either by redesigning products or by otherwise changing societal patterns of consumption, use, or waste generation. See Hawaii Revised Statutes 342G-1

(b) The facility implementation component shall describe the specific tasks that are necessary to provide for the development or expansion of source reduction, recycling, bioconversion, and disposal facility capacity. The planning, design, funding, staffing, siting, construction, and operation of each proposed solid waste facility shall be addressed.
(c) The enterprise zone component shall describe the county’s current and planned actions to establish enterprise zones.