Sec. 10. (a) If the department receives corrections to a plan in response to a notice sent under section 9(2) of this chapter, and any time the department receives corrections to a notice under subdivision (2) thereafter, the department shall do one (1) of the following:

(1) Not later than ten (10) business days after receiving the corrections, send notice to the applicant that the corrected plans have been approved for a design release as submitted. The department shall, not later than the next business day after the date that notice is sent to the applicant, provide to the applicant:

Terms Used In Indiana Code 22-15-3.2-10

(A) a copy of the design release; or

(B) a confirmation number that serves as a temporary design release until the applicant receives a copy of the design release.

(2) Not later than ten (10) business days after receiving the corrections, send notice to the applicant that a design release will not be issued until the applicant submits additional corrections. However, if the applicant does not receive the notice within the period specified in this subdivision, the department shall, not later than the eleventh business day after the date that the corrections are received by the department, provide the applicant with:

(A) a copy of the design release; or

(B) a confirmation number that serves as a temporary design release until the applicant receives a copy of the design release.

     (b) A review under this section is limited to the corrections required by the department pursuant to notice sent under section 9(2) of this chapter or subsection (a)(2). All other parts of a project not directly related to corrections required by the department, including previously completed corrections that the department has already accepted, are deemed approved for a design release and may not be included in subsequent notice requests sent under this section. Except for a project reviewed under IC 22-15-3-6 and subject to the deadlines set forth in this chapter, the department may delay issuing a design release until all corrections to a project have been accepted by the department.

As added by P.L.218-2014, SEC.14. Amended by P.L.187-2021, SEC.108.