1. A subcontractor shall post a preliminary notice to the mechanics’ notice and lien registry internet site. A preliminary notice posted before the balance due is paid to the general contractor or the owner-builder is effective as to all labor, service, equipment, and material furnished to the property by the subcontractor. The preliminary notice shall contain all of the following information:

 a. The name of the owner.
 b. The mechanics’ notice and lien registry number.
 c. The name, address, and telephone number of the subcontractor furnishing the labor, service, equipment, or material.
 d. The name and address of the person who contracted with the claimant for the furnishing of the labor, service, equipment, or material.
 e. The name of the general contractor or owner-builder under which the claimant is performing or will perform the work.
 f. The address of the property or a description of the location of the property if the property cannot be reasonably identified by an address.
 g. The legal description that adequately describes the property to be charged with the lien.
 h. The date the material or materials were first furnished or the labor was first performed.
 i. The tax parcel identification number.
 j. Any other information required by the administrator pursuant to rule.

Need help reviewing a real estate contract?
Have it reviewed by a lawyer, get answers to your questions and move forward with confidence.
Connect with a lawyer now

Terms Used In Iowa Code 572.13B

  • Affidavit: A written statement of facts confirmed by the oath of the party making it, before a notary or officer having authority to administer oaths.
  • Evidence: Information presented in testimony or in documents that is used to persuade the fact finder (judge or jury) to decide the case for one side or the other.
  • following: when used by way of reference to a chapter or other part of a statute mean the next preceding or next following chapter or other part. See Iowa Code 4.1
  • Internet: means the federated international system that is composed of allied electronic communication networks linked by telecommunication channels, that uses standardized protocols, and that facilitates electronic communication services, including but not limited to use of the world wide web; the transmission of electronic mail or messages; the transfer of files and data or other electronic information; and the transmission of voice, image, and video. See Iowa Code 4.1
  • Internet site: means a specific location on the internet that is determined by internet protocol numbers, by a domain name, or by both, including but not limited to domain names that use the designations ". See Iowa Code 4.1
  • Lien: A claim against real or personal property in satisfaction of a debt.
  • person: means individual, corporation, limited liability company, government or governmental subdivision or agency, business trust, estate, trust, partnership or association, or any other legal entity. See Iowa Code 4.1
  • property: includes personal and real property. See Iowa Code 4.1
  • Rule: includes "regulation". See Iowa Code 4.1
 2. At the time a preliminary notice is posted to the mechanics’ notice and lien registry internet site, the administrator shall send notification to the owner, including the owner notice described in section 572.13, subsection 1, and shall post the mailing of the notice on the mechanics’ notice and lien registry internet site as prescribed by the administrator pursuant to rule. Notices under this section shall not be sent to owner-builders. Upon request, the administrator shall provide proof of service at no cost for the notice required under this section.
 3. a. A mechanic’s lien perfected under this chapter is enforceable only to the extent of the balance due the general contractor or the owner-builder at the time of the posting of the preliminary notice specified in subsection 1, and, except for residential construction property owned by an owner-builder, also is enforceable only to the extent of the balance due the general contractor at the time the owner actually receives the notice provided pursuant to subsection 2 or paragraph “b”.

 b. (1) In any action to enforce a mechanic’s lien perfected under this chapter against the owner, the subcontractor bears the burden to prove by a preponderance of the evidence that the owner received notice pursuant to subsection 2. A subcontractor may satisfy the burden of proof by providing separate notice to an owner by including but not limited to any of the following means:

 (a) By certified mail with return receipt.
 (b) By personal service in the manner original notices are required to be served.
 (c) By actual notice with a signed receipt from the owner acknowledging notice.
 (2) If the subcontractor provides an affidavit of mailing, the presumption is that the owner received the notice on the fourth day of business for the post office after the notice was sent and the burden of proof shifts from the subcontractor to the owner to refute the presumption.
 4. A subcontractor who fails to post a preliminary notice pursuant to this section shall not be entitled to a lien and remedy provided under this chapter.
 5. This section applies only to residential construction properties.