(1) Except as otherwise provided in subsections (2) and (3), dams and impoundments in the state are under the jurisdiction of the department.
  (2) The following are exempt from this part:

Terms Used In Michigan Laws 324.31506

  • Department: means the director of the department of natural resources or his or her designee to whom the director delegates a power or duty by written instrument. See Michigan Laws 324.301
  • Jurisdiction: (1) The legal authority of a court to hear and decide a case. Concurrent jurisdiction exists when two courts have simultaneous responsibility for the same case. (2) The geographic area over which the court has authority to decide cases.
  • Person: means an individual, partnership, corporation, association, governmental entity, or other legal entity. See Michigan Laws 324.301
  • state: when applied to the different parts of the United States, shall be construed to extend to and include the District of Columbia and the several territories belonging to the United States; and the words "United States" shall be construed to include the district and territories. See Michigan Laws 8.3o
  • United States: shall be construed to include the district and territories. See Michigan Laws 8.3o
  (a) Projects licensed, projects that have preliminary permits, or projects for which an application for licensure has been filed under the federal power act, chapter 285, 41 Stat. 1063, 16 U.S.C. § 791a to 793, 796 to 797, 798 to 818, 820 to 824a, and 824b to 825r, if federal dam safety inspection provisions apply during the license period and the inspection reports are provided to the department.
  (b) Projects located on boundary waters under the jurisdiction and supervision of the United States army corps of engineers.
  (c) Impoundments licensed pursuant to part 115 that contain or are designed to contain type III wastes as defined in rules promulgated under that part.
  (3) Until January 1, 1998, a permit shall not be required under this part for the repair, reconstruction, or improvement of a dam, a portion of which is at least 75 years old, was damaged or destroyed by an act of God and is located in a county that has a per capita income of less than $8,500.00. However, a person who is performing a project for the repair, reconstruction, or improvement of a dam that is exempt from obtaining a permit under this subsection shall submit to the department and the joint capital outlay committee plans and specifications for the project. These plans and specifications shall be prepared by a licensed professional engineer and shall meet acceptable standards in the industry in order for a dam to be repaired, reconstructed, or improved. In reviewing plans and specifications for the project, the joint capital outlay committee may recommend environmental considerations to protect water quality such as underspill devices, minimum flow releases and removal of contaminated sediments that may be resuspended in the water column upon impoundment. Such contaminated sediments shall be disposed of in accordance with state law.