75-26-309. Release of bond — use of bond by department. (1) (a) Subject to subsection (1)(b), the department shall release the bond if it is satisfied that an owner has properly decommissioned a wind generation facility or solar facility in accordance with the plan required in 75-26-304.

Terms Used In Montana Code 75-26-309

  • Contract: A legal written agreement that becomes binding when signed.
  • Department: means the department of environmental quality provided for in 2-15-3501. See Montana Code 75-26-301
  • Owner: means a person who owns a wind generation or solar facility used for the generation of electricity. See Montana Code 75-26-301
  • Solar facility: means an installation or combination of solar panels or plates, including a canopy or array, that captures and converts solar radiation to produce electricity and includes flat plate, focusing solar collectors, or photovoltaic solar cells that:

    (a)has a nameplate capacity greater than or equal to 2 megawatts; and

    (b)produces electricity that is not consumed on the premises of the solar facility or on land immediately adjacent to the premises of the solar facility. See Montana Code 75-26-301

  • Wind generation facility: means any combination of a physically connected wind turbine or turbines, associated prime movers, and other associated property, including appurtenant land and improvements and personal property, that are normally operated together to produce electric power from wind and that have a nameplate capacity greater than or equal to 25 megawatts. See Montana Code 75-26-301

(b)At any time, an owner of a wind generation facility or solar facility may petition the department for release of the bond, and the department shall reply with a determination within 90 days.

(2)If the owner of a wind generation facility or solar facility fails to properly decommission a wind generation facility or solar facility and has not commenced action to rectify deficiencies within 90 days after notification by the department, the department shall cause the bond to be forfeited. The department, with staff, equipment, and material under its control or by contract with others, may take any necessary actions to decommission the wind generation facility or solar facility.