85-15-212. Operating permit. (1) An operation plan must be prepared by the owner and approved by the department prior to operation of the high-hazard dam or reservoir. The operation plan must set forth at a minimum:

Ask a legal question, get an answer ASAP!
Click here to chat with a lawyer about your rights.

(a)a reservoir operation procedure;

(b)a maintenance procedure for the high-hazard dam and appurtenant works; and

(c)emergency procedures and warning plans.

(2)When construction is complete and if the high-hazard dam or reservoir conforms to the construction permit and when an operation plan has been approved, the department shall issue a permit to operate the high-hazard dam or reservoir, containing conditions on the safe operation of the high-hazard dam as it considers necessary.