Any contract not completed within the time specified shall be reestimated and relet to the lowest responsible bidder, but not for a sum greater than the estimate, nor a second time to the same party; Provided, the county board, may for a good cause, extend the time of any contractors not to exceed two years.
Source
- Laws 1881, c. 51, § 20, p. 243;
- Laws 1885, c. 94, § 1, p. 373;
- Laws 1911, c. 140, § 20, p. 460;
- R.S.1913, § 1737;
- C.S.1922, § 1684;
- C.S.1929, § 31-120;
- R.S.1943, § 31-120.
Terms Used In Nebraska Statutes 31-120
- Contract: A legal written agreement that becomes binding when signed.