1.    Liens perfected under this chapter have priority in the following order:

Need help reviewing a real estate contract?
Have it reviewed by a lawyer, get answers to your questions and move forward with confidence.
Connect with a lawyer now

Terms Used In North Dakota Code 35-27-22

  • following: when used by way of reference to a chapter or other part of a statute means the next preceding or next following chapter or other part. See North Dakota Code 1-01-49

a.    For manual labor. b.    For materials.

c.    Subcontractors other than manual laborers.

d.    Original contractors.

2.    Liens for manual labor filed within the ninety-day period must share ratably in the security. Liens for manual labor filed after the ninety-day period have priority in the order of the filing of such liens. Liens for materials filed within the ninety-day period must share ratably in the security and liens filed after the ninety-day period have priority in the order of the filing of such liens.