Distribution facilities belonging to another electrical utility which, after July 9, 1973, are located in the present service area of the Public Service Authority as defined in § 58-31-330, shall be acquired by the Public Service Authority within two years of July 9, 1973 and upon payment to the electrical utility concerned of just compensation therefor. Pending the acquisition of such facilities by the Public Service Authority, electrical service shall continue to be furnished by the electrical utility owning the facilities.

For the purposes of this section, "just compensation" shall consist of the total of the following:

Terms Used In South Carolina Code 58-31-350

  • electrical utility: includes persons and corporations, their lessees, assignees, trustees, receivers or other successors in interest owning or operating in this State equipment or facilities for generating, transmitting, delivering or furnishing electricity for street, railway or other public uses or for production of light, heat or power to or for the public for compensation; but it shall not include an electric cooperative or municipality and shall not include a person, corporation furnishing electricity only to himself or itself, their residents, employees or tenants when such electricity is not resold or used by others. See South Carolina Code 58-31-310
  • line: includes any electric conductor operating at a nominal voltage level in excess of 25 KV when it is agreed between the Public Service Authority and an affected electric cooperative serving in the county where the conductor is located that the primary purpose and use of the conductor on January 1, 1984, was for the distribution of electric power and not for the transmission of bulk power from one area to another. See South Carolina Code 58-31-310
  • present service area: means the area or areas hereinafter described, within which the Public Service Authority shall have the right to furnish electrical service to the exclusion of other electrical utilities. See South Carolina Code 58-31-310

(a) Reproduction cost, new, of the facilities being acquired, less depreciation on a straight line basis;

(b) Cost of reintegrating the system of the selling electrical utility after detaching the portion to be sold including allowance for idle substation capacity caused in the remaining portion of the system.

Just compensation shall otherwise be determined as provided in § 58-27-1360.