A drain may be constructed along a rail line, if necessary, if no damage is done to the rail line. If it is necessary to cross a railroad rightofway, the railroad company, if so ordered by the board, shall make necessary openings through the rightofway and construct and maintain culverts or bridges to permit free and unobstructed flow of water across the rightofway. The cost of such construction and maintenance, except the cost of excavating the ditch across the rightofway, shall be borne as outlined in § 46A-10A-74. Service of such order shall be made upon the railroad company in the manner provided for the service of summons in a civil action. An order directing construction of a drainage bridge or culvert shall be served upon the railroad company. The railroad company shall have sixty days after the service of an order to construct the bridge or culvert.

Terms Used In South Dakota Codified Laws 46A-10A-73

  • Summons: Another word for subpoena used by the criminal justice system.

Source: SL 1985, ch 362, § 74; SL 1986, ch 379, § 9.