(a) The contract price of any construction contract of the authority may be paid in partial payments as the work progresses, but the payments may not exceed 90 percent of the amount due at the time of the payments as shown by the authority engineer’s report.
(b) The executive director shall, at all times during the progress of the work, inspect the work or have the work inspected by the authority engineer or the engineer’s assistants.

Ask a legal question, get an answer ASAP!
Click here to chat with a lawyer about your rights.

Terms Used In Texas Special District Local Laws Code 8511.0322

  • Contract: A legal written agreement that becomes binding when signed.

(c) On certification of the executive director and the authority engineer of the completion of the contract in accordance with its terms and, in the case of any construction contract for which notice to bidders is required by § 8511.0321(c), on board approval, the authority shall draw a warrant on its depository to pay the balance due on the contract.