Washington Code 39.04.240 – Public works contracts — Awarding of attorneys’ fees
Current as of: 2023 | Check for updates
|
Other versions
(1) The provisions of RCW 4.84.250 through 4.84.280 shall apply to an action arising out of a public works contract in which the state or a municipality, or other public body that contracts for public works, is a party, except that: (a) The maximum dollar limitation in RCW 4.84.250 shall not apply; and (b) in applying RCW 4.84.280, the time period for serving offers of settlement on the adverse party shall be the period not less than thirty days and not more than one hundred twenty days after completion of the service and filing of the summons and complaint.
Terms Used In Washington Code 39.04.240
- Complaint: A written statement by the plaintiff stating the wrongs allegedly committed by the defendant.
- Contract: A legal written agreement that becomes binding when signed.
- Settlement: Parties to a lawsuit resolve their difference without having a trial. Settlements often involve the payment of compensation by one party in satisfaction of the other party's claims.
- Summons: Another word for subpoena used by the criminal justice system.
(2) The rights provided for under this section may not be waived by the parties to a public works contract that is entered into on or after June 11, 1992, and a provision in such a contract that provides for waiver of these rights is void as against public policy. However, this subsection shall not be construed as prohibiting the parties from mutually agreeing to a clause in a public works contract that requires submission of a dispute arising under the contract to arbitration.