(a) An applicant for approval of a major subdivision or land development plan and plat shall submit written application, a copy of the proposed land development plan and plat, and the fees to the planning commission having jurisdiction over the land.

Ask a real estate law question, get an answer ASAP!
Thousands of highly rated, verified real estate lawyers.
Specialties include: All Real Estate Law, Landlord and Tenant Law, Foreclosure, Homeowners' Association, Trespassing, Property Law, General Legal and more.
Click here to chat with a lawyer about your rights.

Terms Used In West Virginia Code 8A-5-6

  • in writing: includes any representation of words, letters, or figures, whether by printing, engraving, writing, or otherwise. See West Virginia Code 2-2-10
  • Jurisdiction: (1) The legal authority of a court to hear and decide a case. Concurrent jurisdiction exists when two courts have simultaneous responsibility for the same case. (2) The geographic area over which the court has authority to decide cases.
  • Land development: means the development of one or more lots, tracts or parcels of land by any means and for any purpose, but does not include easements, rights-of-way or construction of private roads for extraction, harvesting or transporting of natural resources. See West Virginia Code 8A-1-2
  • Plan: means a written description for the development of land. See West Virginia Code 8A-1-2
  • Planning commission: means a municipal planning commission, a county planning commission, a multicounty planning commission, a regional planning commission or a joint planning commission. See West Virginia Code 8A-1-2
  • Plat: means a map of the land development that becomes its official recorded representation in the office of the clerk of the county commission where a majority of the land to be developed lies. See West Virginia Code 8A-1-2

(b) Within 45 days after receipt of the application, the planning commission, or its staff if the planning commission has delegated such authority, shall review the application for completeness and either accept or deny it: Provided, That if the planning commission’s next regularly scheduled meeting that would meet public notice requirements is scheduled within 60 days of receipt of the application, it may review the application for completeness and either accept or deny it at its next regularly scheduled meeting.

(c) If the application is not complete, then the planning commission may deny the application and must notify the applicant in writing stating the reasons for the denial.