New Jersey Statutes 48:3-17.13. Notification of public utilities; examination of underground utility facility
b. Notwithstanding the notification requirements of subsection a. of section 2 of P.L.2021, c.263 (C. 48:3-17.12), within 60 days of the receipt of the notice required pursuant to subsection a. of this section, a public utility shall examine any underground utility facility owned or operated by the public utility within the borders of a local unit to the extent feasible and notify the local unit and any relevant local utility whether an underground utility facility needs repair or replacement and if the public utility intends to construct a public utility infrastructure project within the scope of the local infrastructure project. The local unit, local utility, and public utility shall coordinate to provide timely notification of any changes to their respective project plans or schedule and, when feasible, to jointly establish a timeframe for scheduled work.
L.2021, c.263, s.3.