Sec. 4. (a) Estimated project costs submitted under section 3(b)(5) of this chapter must include the following:

(1) Eligible project costs.

(2) Ineligible project costs.

     (b) Project costs that are ineligible for grant funding may not be used to fulfill a grantee’s match requirement. A grantee is responsible for all project costs except the costs funded by a grant.

     (c) Ineligible project costs include the following:

(1) Costs incurred before the approval of a grant.

(2) Costs incurred more than twenty-four (24) months after a grant has been accepted.

(3) Costs incurred by a grantee that exceed original estimated eligible project costs indicated in a grant application.

(4) Other costs that are not specifically related to a project as determined by the department.

     (d) Eligible project costs may be:

(1) used to fulfill the grantee’s match requirement; and

(2) funded by the grant.

     (e) Project costs that are not ineligible under subsection (c) are eligible project costs for purposes of subsection (d).

[Pre-1996 Recodification Citation: 13-7-33-9.]

As added by P.L.1-1996, SEC.10. Amended by P.L.237-1999, SEC.6.