Indiana Code 8-1-31.6-13. Allowable recovery for municipally owned utility; factors
Current as of: 2023 | Check for updates
|
Other versions
Sec. 13. In determining the amount of allowable recovery of customer lead service line improvement costs for a municipally owned utility, the commission may consider the following factors:
(2) Debt service on funds borrowed to pay for customer lead service line improvements.
(1) Extensions and replacements, to the extent that the extensions and replacements are not provided for through depreciation, in the manner provided for in IC 8-1.5-3-8.
Terms Used In Indiana Code 8-1-31.6-13
- commission: refers to the Indiana utility regulatory commission created by IC 8-1-1-2. See Indiana Code 8-1-31.6-1
- customer lead service line improvement: means an expenditure that is:
Indiana Code 8-1-31.6-2
(3) Depreciation expenses on customer lead service line improvements based on the same rate or rates of depreciation approved by the commission for the calculation of depreciation in the utility’s most recent rate case.
(4) Other components that the commission considers appropriate.
As added by P.L.137-2020, SEC.11.