Sec. 22. (a) An application for a permit for collocation must include only the following:

(1) All information required by section 19 of this chapter.

Terms Used In Indiana Code 8-1-32.3-22

  • collocation: means the placement or installation of wireless facilities on existing structures that include a wireless facility or a wireless support structure, including water towers and other buildings or structures. See Indiana Code 8-1-32.3-4
  • Evidence: Information presented in testimony or in documents that is used to persuade the fact finder (judge or jury) to decide the case for one side or the other.
  • in writing: include printing, lithographing, or other mode of representing words and letters. See Indiana Code 1-1-4-5
  • Jurisdiction: (1) The legal authority of a court to hear and decide a case. Concurrent jurisdiction exists when two courts have simultaneous responsibility for the same case. (2) The geographic area over which the court has authority to decide cases.
  • permit authority: means a unit, a board, a commission, or any other governing body that makes legislative or administrative decisions concerning the construction, installation, modification, or siting of wireless facilities or wireless support structures. See Indiana Code 8-1-32.3-8
(2) Evidence of conformance with applicable building permit requirements.

     (b) An application for a permit for collocation:

(1) is not required to comply with zoning or land use requirements; and

(2) is not subject to public hearing.

     (c) A permit authority shall allow an applicant to submit a single consolidated application to collocate multiple wireless service facilities that are located within the jurisdiction of the permit authority. The permit authority shall issue a single permit for all wireless service facilities included in the application rather than individual permits for each wireless service facility.

     (d) A permit authority shall review an application within ten (10) business days of its receipt to determine if the application is complete. If a permit authority determines that an application is not complete, the permit authority shall notify the applicant in writing of all defects in the application. If a permit authority does not notify an applicant in writing of all defects in the application, the application is considered complete.

     (e) An applicant that receives a written notice under subsection (d) may cure the defects set forth in the notice and resubmit the corrected application to the permit authority within fifteen (15) days of receiving the notice. If an applicant is unable to cure the defects within the fifteen (15) day period, the applicant shall notify the permit authority of the additional time the applicant requires to cure the defects.

     (f) Not more than forty-five (45) days after making an initial determination of completeness under subsection (d), a permit authority shall:

(1) review the application to determine its conformity with applicable building permit requirements; and

(2) notify the applicant in writing whether the application is approved or denied.

However, if the applicant requested additional time under subsection (e) to cure defects in the application, the forty-five (45) day period is extended for a corresponding amount of time.

As added by P.L.145-2015, SEC.3.