Terms Used In Michigan Laws 324.63407

  • Amendment: A proposal to alter the text of a pending bill or other measure by striking out some of it, by inserting new language, or both. Before an amendment becomes part of the measure, thelegislature must agree to it.
  • Conformance bond: means a surety bond that has been executed by a surety company authorized to do business in this state, cash, a certificate of deposit, a letter of credit, or other security filed by a person and accepted by the department to ensure compliance with this part or rules promulgated under this part. See Michigan Laws 324.63401
  • Department: means the department of environmental quality. See Michigan Laws 324.63401
  • Life of the mine: means the period from initiation of mining activities through the completion of reclamation. See Michigan Laws 324.63401
  • mining: means an operation to excavate or remove earth material that generates not less than 10,000 tons and not more than 75,000 tons of waste rock in a calendar year or disturbs not less than 1 acre and not more than 10 acres of land in a calendar year in the regular operation of a business for the primary purpose of extracting native copper by 1 or both of the following:
    (i) Removing the overburden lying above natural deposits of native copper and excavating directly from the natural deposits thus exposed or by excavating directly from deposits lying exposed in their natural state. See Michigan Laws 324.63401
  • Mining area: means all of the following:
  •     (i) Land from which material is removed by surface or open pit mining methods. See Michigan Laws 324.63401
  • permit: means a permit issued under section 63405 for conducting mining activities. See Michigan Laws 324.63401
  • Permittee: means a person that holds a mining permit. See Michigan Laws 324.63401
  • Person: means an individual, partnership, corporation, association, governmental entity, or other legal entity. See Michigan Laws 324.301
  •     (1) A mining permit is valid for the life of the mine. However, the department may revoke a permit if the permittee has not commenced mining activities covered by the permit within 3 years after the date of issuance of the permit.
        (2) The department may terminate a mining permit upon request of the permittee if the department determines that the permittee has complied with all applicable provisions of this part.
        (3) A mining permit may be transferred with approval of the department. The person seeking to acquire the permit shall submit a request for transfer of the permit to the department on forms provided by the department. The person acquiring the permit shall accept the conditions of the existing permit and adhere to the requirements set forth in the approved mining and reclamation plan and provide a conformance bond as set forth in section 63409. Pending the transfer of the existing permit, the person seeking to acquire the permit shall not operate the mine.
        (4) A mining permit shall not be transferred to a person who has been determined by the department to be in violation of this part, rules promulgated under this part, or a condition of a permit issued under this part, until the person acquiring the permit has corrected the violation or the department has accepted a compliance schedule and the person that will acquire the permit has entered into a written consent agreement to correct the violation.
        (5) If the permittee has been notified by the department of a violation of this part, rules promulgated under this part, or a condition of the permit issued under this part at the mining area involved in the transfer, the mining permit shall not be transferred to a person until the permittee has corrected the violation or the person that will acquire the permit has entered into a written consent agreement to correct the violation.
        (6) A mining permit may be amended upon submission to the department of a request by the permittee. The department shall determine whether the requested amendment constitutes a significant change to the mining and reclamation plan. If the department determines that the requested amendment constitutes a significant change, the department shall submit the request for amendment to the same review process as provided for a new permit application in section 63405(4) to (8). If the department determines that the requested amendment does not constitute a significant change, the department shall approve the request within 14 days after receiving the request.