20 CFR 670.985 – What happens if a center operator, screening and admissions contractor or other service provider fails to meet the expected levels of performance?
Current as of: 2024 | Check for updates
|
Other versions
(a) The Secretary takes appropriate action to address performance issues through a specific performance plan.
Terms Used In 20 CFR 670.985
- Contract: A legal written agreement that becomes binding when signed.
(b) The plan may include the following actions:
(1) Providing technical assistance to a Job Corps center operator or support service provider, including a screening and admissions contractor;
(2) Changing the management staff of a center;
(3) Changing the vocational training offered at a center;
(4) Contracting out or recompeting the contract for a center or operational support service provider;
(5) Reducing the capacity of a Job Corps center;
(6) Relocating a Job Corps center; or
(7) Closing a Job Corps center. (WIA sec. 159 (f).)