Rhode Island General Laws 23-27.3-128.5.4. Building permit issuance or requirements
Current as of: 2024 | Check for updates
|
Other versions
The waiver of the detailed plan examination and/or detailed field inspection shall be determined prior to the issuance of any permits and may be a prerequisite for the permit issuance. Refusal by the owner to provide such service as required by the building official shall result in the denial of the permit. However, the owner may file an appeal as provided in § 23-27.3-127.1 or § 23-27.3-127.2.
History of Section.
P.L. 1988, ch. 222, § 2.
Terms Used In Rhode Island General Laws 23-27.3-128.5.4
- Appeal: A request made after a trial, asking another court (usually the court of appeals) to decide whether the trial was conducted properly. To make such a request is "to appeal" or "to take an appeal." One who appeals is called the appellant.