33 USC 2341b – Prioritization of certain projects
Current as of: 2024 | Check for updates
|
Other versions
The Secretary shall give priority to a project for flood risk management if—
(1) there is an executed project partnership agreement for the project; and
(2) the project is located in an area—
(A) with respect to which—
(i) there has been a loss of life due to flood events; and
(ii) the President has declared that a major disaster or emergency exists under section 5170 of title 42; or
(B) that is at significant risk for catastrophic flooding.
Terms Used In 33 USC 2341b
- Partnership: A voluntary contract between two or more persons to pool some or all of their assets into a business, with the agreement that there will be a proportional sharing of profits and losses.