(a) Report and management plan

The Secretary shall submit to the Congress a report and management plan for any major construction project involving $100,000,000 or more, prior to the expenditure of those funds.

(b) Congressional review

Ask a business law question, get an answer ASAP!
Thousands of highly rated, verified business lawyers.
Click here to chat with a lawyer about your rights.

Expenditure of funds for a project described in subsection (a) may be made after a period of 30 calendar days (not including any day on which either House of Congress is not in session because of adjournment of more than 3 calendar days prior to a day certain) has passed after receipt of the report and management plan by Congress.