A. No utility may construct a plant or transmission line within this state until it has received a certificate of environmental compatibility from the committee with respect to the proposed site, affirmed and approved by an order of the commission which shall be issued not less than thirty days nor more than sixty days after the certificate is issued by the committee, except that within fifteen days after the committee has rendered its written decision any party to a certification proceeding may request a review of the committee’s decision by the commission.

Terms Used In Arizona Laws 40-360.07

  • Affirmed: In the practice of the appellate courts, the decree or order is declared valid and will stand as rendered in the lower court.
  • Appeal: A request made after a trial, asking another court (usually the court of appeals) to decide whether the trial was conducted properly. To make such a request is "to appeal" or "to take an appeal." One who appeals is called the appellant.
  • Certificate of environmental compatibility: means the certificate that is required by this article and that evidences the approval by the state of the sites for a plant or transmission line, or both. See Arizona Laws 40-360
  • Commission: means the corporation commission. See Arizona Laws 40-360
  • Committee: means the power plant and transmission line siting committee. See Arizona Laws 40-360
  • including: means not limited to and is not a term of exclusion. See Arizona Laws 1-215
  • Oral argument: An opportunity for lawyers to summarize their position before the court and also to answer the judges' questions.
  • Person: means any state or agency or political subdivision thereof, or any individual, partnership, joint venture, corporation, city or county, whether located within or without this state, or any combination of such entities. See Arizona Laws 40-360
  • Plant: means each separate thermal electric, nuclear or hydroelectric generating unit with a nameplate rating of one hundred megawatts or more for which expenditures or financial commitments for land acquisition, materials, construction or engineering exceeding $50,000 have not been made before August 13, 1971. See Arizona Laws 40-360
  • Transcript: A written, word-for-word record of what was said, either in a proceeding such as a trial or during some other conversation, as in a transcript of a hearing or oral deposition.
  • Transmission line: means five or more new structures that span more than one mile in length as measured from the first structure outside of the substation, switchyard or generating site to which the line connects to the fifth structure and that are erected above ground and support one or more conductors designed for the transmission of electric energy at nominal voltages of one hundred fifteen thousand volts or more and all new switchyards to be used therewith and related thereto for which expenditures or financial commitments for land acquisition, materials, construction or engineering exceeding $50,000 have not been made before August 13, 1971. See Arizona Laws 40-360
  • Utility: means any person engaged in the generation or transmission of electric energy. See Arizona Laws 40-360

B. The grounds for review shall be stated in a written notice filed with the commission with a copy thereof served on the chairman of the committee. The committee shall transmit to the commission the complete record, including a certified transcript, and the review shall be conducted on the basis of the record. The commission may, at the request of any party, require written briefs or oral argument and shall within sixty days from the date the notice is filed either confirm, deny or modify any certificate granted by the committee, or in the event the committee refused to grant a certificate, the commission may issue a certificate to the applicant. In arriving at its decision, the commission shall comply with the provisions of Section 40-360.06 and shall balance, in the broad public interest, the need for an adequate, economical and reliable supply of electric power with the desire to minimize the effect thereof on the environment and ecology of this state.

C. The committee or any party to a decision by the commission pursuant to subsection B of this section may request the commission to reconsider its decision within thirty days after the decision is issued. A request for reconsideration made pursuant to this subsection shall set forth the grounds upon which it is based and state the manner in which the party believes the commission unreasonably or unlawfully applied or failed to apply the criteria set forth in Section 40-360.06. The decision of the commission is final with respect to all issues, subject only to judicial review as provided by law in the event of an appeal by a person having a legal right or interest that will be injuriously affected by the decision.