Indiana Code 14-37-8-4. Plugging a well immediately after completion of drilling operations
(c) Except as provided in subsection (d), an oil and gas inspector must be present during the plugging of a well.
(d) Subsection (c) does not apply if:
(1) the owner or operator notifies an oil and gas inspector under subsection (b);
(2) as part of the notice the owner or operator informs the oil and gas inspector of the plan for plugging the well; and
(3) the oil and gas inspector gives the owner or operator verbal or written approval of the plan.
[Pre-1995 Recodification Citation: 13-8-10-4.]
As added by P.L.1-1995, SEC.30. Amended by P.L.140-2011, SEC.12.