Iowa Code 572.16 – Rule of construction
Current as of: 2023 | Check for updates
|
Other versions
Terms Used In Iowa Code 572.16
- Contract: A legal written agreement that becomes binding when signed.
- Lien: A claim against real or personal property in satisfaction of a debt.
Nothing in this chapter shall be construed to require the owner to pay a greater amount or at an earlier date than is provided in the owner’s contract with the general contractor, unless the owner pays a part or all of the contract price to the general contractor before the expiration of the ninety days allowed by law for the posting of a mechanic’s lien by a subcontractor; provided that in the case of residential construction, nothing in this chapter shall be construed to require the owner to pay a greater amount or at an earlier date than is provided in the owner’s contract with the general contractor, unless the owner pays a part or all of the contract price to the general contractor after the owner receives notice pursuant to section 572.13B, subsection 2 or section 572.13B, subsection 3, paragraph “b”.