(1) An asbestos abatement contractor shall notify the department in writing of all of the following at least 10 days before beginning an asbestos abatement project exceeding 10 linear feet or 15 square feet, or both, of friable asbestos materials:
  (a) The name and address of the owner of the building or structure.

Terms Used In Michigan Laws 338.3220

  • Asbestos: means a group of naturally occurring minerals that separate into fibers, including chrysotile, amosite, crocidolite, anthophyllite, tremolite, and actinolite. See Michigan Laws 338.3103
  • Asbestos abatement contractor: means a business entity that is licensed under this act and that carries on the business of asbestos abatement on the premises of another business entity and not on the asbestos abatement contractor's premises. See Michigan Laws 338.3103
  • Asbestos abatement project: means any activity involving persons working directly with the demolition, renovation, or encapsulation of friable asbestos materials. See Michigan Laws 338.3103
  • Business entity: means a person, partnership, firm, association, corporation, sole proprietorship, public or private agency, or other legal entity. See Michigan Laws 338.3103
  • Contract: A legal written agreement that becomes binding when signed.
  • Department: means the department of consumer and industry services. See Michigan Laws 338.3103
  • Discovery: Lawyers' examination, before trial, of facts and documents in possession of the opponents to help the lawyers prepare for trial.
  • Fiscal year: The fiscal year is the accounting period for the government. For the federal government, this begins on October 1 and ends on September 30. The fiscal year is designated by the calendar year in which it ends; for example, fiscal year 2006 begins on October 1, 2005 and ends on September 30, 2006.
  • in writing: shall be construed to include printing, engraving, and lithographing; except that if the written signature of a person is required by law, the signature shall be the proper handwriting of the person or, if the person is unable to write, the person's proper mark, which may be, unless otherwise expressly prohibited by law, a clear and classifiable fingerprint of the person made with ink or another substance. See Michigan Laws 8.3q
  • Removal: means the taking out or stripping of asbestos from an existing structure. See Michigan Laws 338.3103
  • state: when applied to the different parts of the United States, shall be construed to extend to and include the District of Columbia and the several territories belonging to the United States; and the words "United States" shall be construed to include the district and territories. See Michigan Laws 8.3o
  (b) The location of the building or structure where the asbestos abatement project will be performed.
  (c) The schedule for the starting and completion of the asbestos abatement project which may not exceed 1 year in length.
  (d) The amount of friable asbestos materials that will be removed or encapsulated.
  (2) If during the course of a project and after a written contract is executed, a business entity that is exempt from licensure under section 207(2) and whose primary licensed trade is not that of an asbestos abatement contractor discovers that the removal or encapsulation of asbestos in an amount exceeding 10 linear feet or 15 square feet, or both, is required, that business entity shall notify the department of the asbestos abatement project before asbestos removal begins. Not more than 10 days after the discovery, the business entity shall provide written notification to the department in the manner described in subsection (1)(a) to (d).
  (3) An asbestos abatement contractor providing written notification to the department pursuant to subsection (1) for an asbestos abatement project shall include a fee equal to 1% of the price of the contract for the asbestos abatement project and shall make available upon the request of the department a copy of the contract for the asbestos abatement project. All fees collected pursuant to this subsection shall be deposited in the asbestos abatement fund created in subsection (5).
  (4) In the case of a business entity that provides notice under subsection (2) for an asbestos abatement project that is incidental to the business entity’s primary licensed trade and where asbestos is actually removed by that business entity, the primary licensed trade contractor shall include a fee of 1% of the asbestos abatement project portion of the contract price and shall make available upon the request of the department a copy of that portion of the contract covering the asbestos abatement. All fees collected pursuant to this subsection shall be deposited in the asbestos abatement fund created in subsection (5).
  (5) The asbestos abatement fund is created and shall exist in the state treasury and shall receive revenue as provided in this act and other revenue as the legislature may provide. The state treasurer shall direct the investment of the fund. All interest and earnings of the fund shall be retained by the fund. Money in the fund at the close of the fiscal year shall remain in the fund and shall not revert to the general fund.
  (6) Money in the asbestos abatement fund created in subsection (5) shall be used by the department only for the asbestos-related responsibilities of the department under this act which includes, but is not limited to, the inspection of asbestos abatement projects and the education of asbestos abatement contractors. It does not include use of the fund by the department for asbestos abatement projects on state owned property.
  (7) Not later than October 1 of each year, the department shall report to the legislature and the applicable committees in the house of representatives and the senate on the amount of money generated by the fees charged under this section. The report shall include the number of asbestos abatement projects inspected and the number of citations issued for violations of this act and other applicable laws, rules, and regulations.
  (8) Emergency asbestos abatement projects resulting from equipment failure or malfunctions are exempt from the 10-day written advance notice imposed under this section. The written notice in emergency situations shall be provided within 48 hours after the commencement of the asbestos abatement project except that the business entity shall contact the department telephonically immediately or as soon as possible after the discovery of the emergency situation.