§ 51-0907. Contracts for municipal solid waste management projects.

Terms Used In N.Y. Environmental Conservation Law 51-0907

  • Commissioner: shall mean the commissioner of environmental conservation except that within and for the purposes of title eleven of this article, the commissioner of parks and recreation. See N.Y. Environmental Conservation Law 51-0101
  • Contract: A legal written agreement that becomes binding when signed.
  • Municipality: except as otherwise defined within this article, shall mean a city, county, town, village, public benefit corporation or school district or an improvement district within a city, county, town or village, or any combination thereof. See N.Y. Environmental Conservation Law 51-0101
  • Source separation equipment: shall mean :

    (a) Add-ons or trailers designed to modify collection vehicles to allow sorting and separation of collected wastes held for the purpose of recycling or collection vehicles whose function and design are exclusively for such purpose;

    (b) Containers for the source separation and temporary storage of recyclable wastes by residents or business prior to collection;

    (c) Bins, sheds or other facilities for the temporary storage of materials prior to transport for the purposes of recycling. See N.Y. Environmental Conservation Law 51-0903

1. The commissioner, in the name of the state, may enter into contracts with municipalities which may include such provisions as may be agreed upon by the parties thereto, and shall include, in substance, the following provisions:

a. An estimate of the reasonable cost of the project as determined by the commissioner.

b. An agreement by the commissioner to pay to the municipality, during the progress of construction or following completion of construction as may be agreed upon by the parties, an amount, not to exceed fifty percent of the cost of resource recovery equipment and source separation equipment, and twenty-five percent of the cost of disposal equipment.

c. An agreement by the municipality:

(1) to proceed expeditiously with, and complete, the project as approved by the commissioner;

(2) to commence operation of the project upon its completion and not to dispose of the project or any portion thereof or change its use without the approval of the commissioner;

(3) to operate and maintain the solid waste management project in accordance with applicable law and rules and regulations of the commissioner;

(4) to apply for and make reasonable efforts to secure federal assistance for the project;

(5) to secure the approval of the commissioner before applying for federal assistance, in order to maximize the amounts of such assistance received or to be received for all projects in New York state;

(6) to provide for the payment of the municipality's share of the cost of the project.

d. A provision that, in the event that federal assistance which was not included in the calculation of the state payment becomes available to the municipality, the amount of the state payment shall be recalculated with the inclusion of such federal assistance and the municipality shall pay to the state the amount by which the state payment actually made exceeds the state payment determined by the recalculation.

2. In connection with each contract, the commissioner shall keep adequate records of the amount of the payment by the state and of the amount of federal assistance, if any, received by the municipality. Such records shall be retained by the commissioner and shall establish the basis for recalculation of the state payment as required herein.