In addition to the provisions of section 24-02-30, full compliance by a contractor with the provisions of this section is a condition precedent to the contractor’s right to demand arbitration.

Terms Used In North Dakota Code 24-02-26.1

  • Contract: A legal written agreement that becomes binding when signed.
  • Department: means the department of transportation of this state as provided by section 24-02-01. See North Dakota Code 24-01-01.1
  • Director: means the director of the department of transportation of this state, acting directly or through authorized agents as provided in section 24-02-01. See North Dakota Code 24-01-01.1
  • Person: means any person, firm, partnership, association, corporation, limited liability company, organization, or business trust. See North Dakota Code 24-01-01.1
  • Precedent: A court decision in an earlier case with facts and law similar to a dispute currently before a court. Precedent will ordinarily govern the decision of a later similar case, unless a party can show that it was wrongly decided or that it differed in some significant way.
  • State: when applied to the different parts of the United States, includes the District of Columbia and the territories. See North Dakota Code 1-01-49
  • written: include "typewriting" and "typewritten" and "printing" and "printed" except in the case of signatures and when the words are used by way of contrast to typewriting and printing. See North Dakota Code 1-01-37

If the contractor believes the contractor is entitled to additional compensation for work or materials not covered in the contract or not ordered by the engineer as extra work or force account work in accordance with the contract specifications, the contractor shall, prior to beginning the work which the claim will be based upon, notify the engineer in writing of the intent to make claim for additional compensation. If the basis for the claim does not become apparent until the contractor has commenced work on the project and it is not feasible to stop the work, the contractor shall immediately notify the engineer that the work is continuing and that written notification of the intent to make claim will be submitted within ten calendar days. Failure of the contractor to give the notification required and to afford the engineer facilities and assistance in keeping strict account of actual costs will constitute a waiver of claim for additional compensation in connection with the work already performed. Notification of a claim, and the fact that the engineer has kept account of the costs involved, may not be construed as proving or substantiating the validity or actual value of the claim.

A contractor submitting a claim for compensation under this section, personally or on behalf of another person or entity, must do so in writing, not later than ninety days after the department has submitted the final estimate to the contractor. The claim must state the monetary amount of the claim, the reason for the claim, when the loss was incurred, and a short statement of the factual situation under which the claim arose. The claim must be made under oath or equivalent affirmation.

The director shall act on claims of less than three million dollars within sixty days after the claim is served upon the director. The director shall act on claims of three million dollars or more within one hundred eighty days after the claim is served upon the director. The contractor and the director may negotiate a supplemental agreement for the claim items that are accepted by the director, and the director shall immediately pay the contractor for any additional compensation resulting from the supplemental agreement. The contractor may demand arbitration on the remaining claim items within ninety days after the contractor has been notified of the director’s action on the claim.

The contractor shall make available to the department and allow the department to examine and copy all of the contractor’s records, documents, worksheets, and other data which are pertinent to the justification of the claim and to the substantiation of all costs related to the claim. The department shall also make available to the contractor all of the department’s records, documents, worksheets, and other data which are pertinent to the department’s response to the claim.