(A) For purposes of this section:

(1) "Development" means any activity, including timber harvesting, that is associated with the conversion of forestland to nonforest or nonagricultural use.

Terms Used In South Carolina Code 48-23-205

  • Appeal: A request made after a trial, asking another court (usually the court of appeals) to decide whether the trial was conducted properly. To make such a request is "to appeal" or "to take an appeal." One who appeals is called the appellant.

(2) "Forestland" means land supporting a stand or potential stand of trees valuable for timber products, watershed or wildlife protection, recreational uses, or for other purposes.

(3) "Forest management plan" means a document or documents prepared or approved by a forester registered in this State that defines a landowner’s forest management objectives and describes specific measures to be taken to achieve those objectives. A management plan shall include silvicultural practices, objectives, and measures to achieve them, that relate to a stand or potential stand of trees that may be utilized for timber products, watershed or wildlife protection, recreational uses, or for other purposes.

(4) "Forestry activity" includes, but is not limited to, timber harvest, site preparation, controlled burning, tree planting, applications of fertilizers, herbicides, pesticides, weed control, animal damage control, fire control, insect and disease control, forest road construction, and any other generally accepted forestry practices.

(B) A county or municipality must not adopt or enforce any ordinance, rule, regulation, resolution, or permit related to forestry activities on forestland that is:

(1) taxed on the basis of its present use value as forestland under § 12-43-220(d);

(2) managed in accordance with a forest management plan;

(3) certified under the Sustainable Forestry Initiative, the Forest Stewardship Council, the American Forest Foundations Tree Farm System, or any other nationally recognized forest certification system;

(4) subject to a legally binding conservation easement under which the owner limits the right to develop or subdivide the land; or

(5) managed and harvested in accordance with the best management practices established by the State Commission of Forestry pursuant to § 48-36-30.

(C) This section does not limit, expand, or otherwise alter the authority of a county or municipality to:

(1) regulate activities associated with development, provided that a county or municipality requires a deferral of consideration of an application for a building permit, a site disturbance or subdivision plan, or any other approval for development that if implemented would result in a change from forest land to nonforest or nonagricultural use, the deferral may not exceed a period of up to:

(a) one year after the completion of a timber harvest if the harvest results in the removal of all or substantially all of the trees from the specific area included in a building permit, site disturbance or subdivision plan in item (1), and the removal qualified for an exemption contained in subsection (B); or

(b) five years after the completion of a timber harvest if the harvest results in the removal of all or substantially all of the trees from the specific area included in a building permit, site disturbance or subdivision plan in item (1), and the removal qualified for an exemption contained in subsection (B) for which the permit or approval is sought and the harvest was a wilful violation of the county regulations;

(2) regulate trees pursuant to any act of the General Assembly;

(3) adopt ordinances that are necessary to comply with any federal or state law, regulation, or rule; or

(4) exercise its development permitting, planning, or zoning authority as provided by law.

(D) A person whose application for a building permit, a site disturbance or subdivision plan, or any other approval for development is deferred pursuant to the provisions contained in this section may appeal the decision to the appropriate governmental authority.