(A)(1) The term "fuel cost" as used in this section includes the cost of fuel, cost of fuel transportation, and fuel costs related to purchased power. "Fuel cost" also shall include the following variable environmental costs: (a) the cost of ammonia, lime, limestone, urea, dibasic acid and catalysts consumed in reducing or treating emissions, and (b) the cost of emission allowances, as used, including allowance for SO2, NOx, mercury, and particulates. Upon application of the utility, and after a hearing at which all interested parties may appear and present evidence, the commission may, if it determines such action to be just and reasonable, allow the variable costs of other environmental reagents, other environmental allowances or emissions-related taxes to be recovered as a component of fuel costs, but only to the extent these variable environmental costs are required to be incurred in relation to the consumption of fuel and the air emissions caused thereby. Alternatively, the commission may decide that the costs related to these other variable environmental costs may only be recovered through base rates established under §§ 58-27-860 and 58-27-870. All variable environmental costs included in fuel costs shall be recovered from each class of customers as a separate environmental component of the overall fuel factor. The specific environmental component for each class of customers shall be determined by allocating such variable environmental costs among customer classes based on the utility’s South Carolina firm peak demand data from the prior year. Fuel costs must be reduced by the net proceeds of any sales of emission allowances by the utility. If capacity costs are permitted to be recovered through the fuel factor, such costs shall be allocated and recovered from customers under a separate capacity component of the overall fuel factor based on the same method that is used by the utility to allocate and recover variable environmental costs. The incremental and avoided costs of distributed energy resource programs and net metering as authorized and approved under Chapters 39 and 40, Title 58 shall be allocated and recovered from customers under a separate distributed energy component of the overall fuel factor that shall be allocated and recovered based on the same method that is used by the utility to allocate and recover variable environmental costs.

(2) In order to clarify the intent of this section, "fuel costs related to purchased power", as used in subsection (A)(1) shall include:

Terms Used In South Carolina Code 58-27-865

  • commission: means the Public Service Commission of this State. See South Carolina Code 58-27-10
  • electrical utility: includes municipalities to the extent of their business, property, rates, transactions, and operations without the corporate limits of the municipality, persons and corporations, their lessees, assignees, trustees, receivers, or other successors in interest owning or operating in this State equipment or facilities for generating, transmitting, delivering, or furnishing electricity for street, railway, or other public uses or for the production of light, heat, or power to or for the public for compensation; but it shall not include an electric cooperative or a consolidated political subdivision and shall not include a person, corporation, or municipality furnishing electricity only to himself or itself, their residents, employees, or tenants when such current is not resold or used by others. See South Carolina Code 58-27-10
  • Evidence: Information presented in testimony or in documents that is used to persuade the fact finder (judge or jury) to decide the case for one side or the other.
  • public: means the public generally or any limited portion of the public, including a person, corporation, or municipality. See South Carolina Code 58-27-10
  • rate: means and includes every compensation, charge, toll, rental, and classification, or any of them, demanded, observed, charged, or collected by any electrical utility for any electric current or service offered by it to the public and any rules, regulations, practices, or contracts affecting any such compensation, charge, toll, rental, or classification. See South Carolina Code 58-27-10
  • regulatory staff: means the executive director or the executive director and the employees of the Office of Regulatory Staff. See South Carolina Code 58-27-10

(a) costs of "firm generation capacity purchases", which are defined as purchases made to cure a capacity deficiency or to maintain adequate reserve levels; costs of firm generation capacity purchases include the total delivered costs of firm generation capacity purchased and shall exclude generation capacity reservation charges, generation capacity option charges, and any other capacity charges;

(b) the total delivered cost of economy purchases of electric power including, but not limited to, transmission charges; "economy purchases" are defined as purchases made to displace higher cost generation, at a price which is less than the purchasing utility’s avoided variable costs for the generation of an equivalent quantity of electric power; and

(c) avoided costs under the Public Utility Regulatory Policy Act of 1978, also known as PURPA.

(B) The commission shall direct each electrical utility which incurs fuel cost for the sale of electricity to submit to the commission and to the Office of Regulatory Staff, within such time and in such form as the commission may designate, its estimates of fuel costs for the next twelve months. The commission may hold a public hearing at any time between the twelve-month reviews to determine whether an increase or decrease in the base rate amount designed to recover fuel cost should be granted. Upon conducting public hearings in accordance with law, the commission shall direct each company to place in effect in its base rate an amount designed to recover, during the succeeding twelve months, the fuel costs determined by the commission to be appropriate for that period, adjusted for the over-recovery or under-recovery from the preceding twelve-month period. The commission shall direct the electrical utilities to send notice to the utility customers with the antecedent billing of the time and place of the public hearings to be held every twelve months, and the commission shall again direct the electrical utilities to send notice to the utility customers with the next billing if the utility is granted a rate increase by the commission.

(C) The commission shall direct the electrical utilities to account monthly for the differences between the recovery of fuel costs through base rates and the actual fuel costs experienced, by booking the difference to unbilled revenues with a corresponding deferred debit or credit, the balance of which will be included in the projected fuel cost component of the base rates for the succeeding period. The commission shall direct the electrical utilities to submit to the Office of Regulatory Staff monthly reports of fuel costs and monthly reports of all scheduled and unscheduled outages of generating units with a capacity of one hundred megawatts or greater.

(D) Upon request by the regulatory staff or the electrical utilities, a public hearing must be held by the commission at any time between the twelve-month reviews to determine whether an increase or decrease in the base rate amount designed to recover fuel costs should be granted. If the request is by an electrical utility for a rate increase, the commission shall direct the utility to send notice of the request and hearing to all customers with the next billing, and if the commission grants the rate request subsequent to the request and hearing, the commission shall direct the utility to send notice of the amount of the increase or decrease to all customers with the next billing.

(E) The commission may offset, to the extent considered appropriate, the cost of fuel recovered through sales of power pursuant to interconnection agreements with neighboring electrical utilities against fuel costs to be recovered.

(F) The commission shall disallow recovery of any fuel costs that it finds without just cause to be the result of failure of the utility to make every reasonable effort to minimize fuel costs or any decision of the utility resulting in unreasonable fuel costs, giving due regard to reliability of service, economical generation mix, generating experience of comparable facilities, and minimization of the total cost of providing service. There shall be a rebuttable presumption that an electrical utility made every reasonable effort to minimize cost associated with the operation of its nuclear generation facility or system, as applicable, if the utility achieved a net capacity factor of ninety-two and one-half percent or higher during the period under review. The calculation of the net capacity factor shall exclude reasonable outage time associated with reasonable refueling, reasonable maintenance, reasonable repair, and reasonable equipment replacement outages; the reasonable reduced power generation experienced by nuclear units as they approach a refueling outage; the reasonable reduced power generation experienced by nuclear units associated with bringing a unit back to full power after an outage; Nuclear Regulatory Commission required testing outages unless due to the unreasonable acts of the utility; outages found by the commission not to be within the reasonable control of the utility; and acts of God. The calculation also shall exclude reasonable reduced power operations resulting from the demand for electricity being less than the full power output of the utility’s nuclear generation system. If the net capacity factor is below ninety-two and one-half percent after reflecting the above specified outage time, then the utility shall have the burden of demonstrating the reasonableness of its nuclear operations during the period under review.

(G) The commission is authorized to promulgate, in accordance with the provisions of this section, all regulations necessary to allow the recovery by electrical utilities of all their prudently incurred fuel costs as precisely and promptly as possible, in a manner that tends to assure public confidence and minimize abrupt changes in charges to consumers.