A. A natural gas utility shall account for the difference between actual monthly eligible system expansion infrastructure costs incurred on the cumulative investment in eligible system expansion infrastructure and revenue collected through a system expansion rider as a deferred cost. Such deferred costs shall be accounted for as a regulatory asset and shall not be subject to write-off or write-down by the Commission in an earnings test filing made pursuant to Commission rules governing utility rate increases and annual informational filings.

Terms Used In Virginia Code 56-612

  • Commission: means the State Corporation Commission. See Virginia Code 56-1
  • Eligible expansion investment: means that portion of the total capital investment made by a natural gas utility in constructing eligible system expansion infrastructure that is in excess of those costs that would be considered economic under a natural gas utility's economic test, net of any contributions in aid of construction, up to the maximum level of investment per affected customer specified in a system expansion plan. See Virginia Code 56-610
  • Eligible system expansion infrastructure: means natural gas main pipelines and associated facilities, including service lines, meters, and other pertinent facilities, that are constructed and operated by a natural gas utility to deliver natural gas service to affected customers located in an unserved area. See Virginia Code 56-610
  • Eligible system expansion infrastructure costs: includes :

    1. See Virginia Code 56-610

  • Natural gas utility: means any investor-owned public service company engaged in the business of furnishing natural gas service to the public. See Virginia Code 56-610
  • Rate: means rate charged for any service rendered or to be rendered. See Virginia Code 56-1
  • regulation: include joint rates, joint charges and joint regulations, respectively. See Virginia Code 56-1
  • System expansion plan: means a plan filed by a natural gas utility that identifies the level of eligible system expansion infrastructure costs that are projected to be incurred over the term of the plan and provides the calculation of a system expansion rider. See Virginia Code 56-610
  • System expansion rider: means a recovery mechanism that will allow for recovery of the eligible system expansion infrastructure costs from affected customers, through a separate mechanism from the customer rates established in a rate case using the cost-of-service methodology set forth in § 56-235. See Virginia Code 56-610

B. If a natural gas utility collects all of the deferred eligible system expansion infrastructure costs, as well as all eligible expansion investment, through a system expansion rider prior to the expiration of the time period specified in its system expansion plan pursuant to clause (ii) of subsection A of § 56-611, the system expansion rider shall terminate. A natural gas utility may extend the system expansion rider beyond the period it is proposed to be in effect if necessary to recover any uncollected deferral or eligible system expansion infrastructure costs. A natural gas utility shall notify the Commission of any termination or extension of a system expansion rider at least 60 days prior to its termination or extension. Such termination or extension of the system expansion rider shall be subject to Commission approval.

C. Deferral of costs recovered pursuant to this chapter shall have no effect on the recovery of any other cost by the natural gas utility and shall not be included in any computation relative to a performance-based regulation plan revenue-sharing mechanism.

2015, cc. 28, 231.