Terms Used In 42 USC 16357

  • Baseline: Projection of the receipts, outlays, and other budget amounts that would ensue in the future without any change in existing policy. Baseline projections are used to gauge the extent to which proposed legislation, if enacted into law, would alter current spending and revenue levels.
  • Fiscal year: The fiscal year is the accounting period for the government. For the federal government, this begins on October 1 and ends on September 30. The fiscal year is designated by the calendar year in which it ends; for example, fiscal year 2006 begins on October 1, 2005 and ends on September 30, 2006.

(a) Facility and infrastructure policy

(1) In general

The Secretary shall develop and implement a strategy for facilities and infrastructure supported primarily from the Office of Science, the Office of Energy Efficiency and Renewable Energy, the Office of Fossil Energy, or the Office of Nuclear Energy, Science and Technology Programs at all National Laboratories and single-purpose research facilities.

(2) Strategy

The strategy shall provide cost-effective means for—

(A) maintaining existing facilities and infrastructure;

(B) closing unneeded facilities;

(C) making facility modifications; and

(D) building new facilities.

(b) Report

(1) In general

The Secretary shall prepare and submit, along with the budget request of the President submitted to Congress for fiscal year 2018, a report describing the strategy developed under subsection (a).

(2) Contents

For each National Laboratory and single-purpose research facility that is primarily used for science and energy research, the report shall contain—

(A) the current priority list of proposed facilities and infrastructure projects, including cost and schedule requirements;

(B) a current 10-year plan that demonstrates the reconfiguration of its facilities and infrastructure to meet its missions and to address its long-term operational costs and return on investment;

(C) the total current budget for all facilities and infrastructure funding; and

(D) the current status of each facility and infrastructure project compared to the original baseline cost, schedule, and scope.