(a) The commission must use a two-phase procedure for the selection of the successful design-build entity. Phase I of the procedure will evaluate and shortlist the design-build entities based on qualifications, and Phase II will evaluate the technical and cost proposals.
     (b) The commission shall include in the request for proposal the evaluating factors to be used in Phase I. These factors are in addition to any prequalification requirements of design-build entities that the commission has set forth. Each request for proposal shall establish the relative importance assigned to each evaluation factor and subfactor, including any weighting of criteria to be employed by the commission. The commission must maintain a record of the evaluation scoring to be disclosed in event of a protest regarding the solicitation.

Terms Used In Illinois Compiled Statutes 65 ILCS 5/11-135.5-60

  • Contract: A legal written agreement that becomes binding when signed.
  • Design professional: means any individual, sole proprietorship, firm, partnership, joint venture, corporation, professional corporation, or other entity that offers services under the Illinois Architecture Practice Act of 1989, the Professional Engineering Practice Act of 1989, the Structural Engineering Practice Act of 1989, or the Illinois Professional Land Surveyor Act of 1989. See Illinois Compiled Statutes 65 ILCS 5/11-135.5-7
  • Design-build: means a delivery system that provides responsibility within a single contract for the furnishing of architecture, engineering, land surveying, and related services as required and the labor, materials, equipment, and other construction services for the project. See Illinois Compiled Statutes 65 ILCS 5/11-135.5-7
  • Design-build contract: means a contract for a public project under this Division between a commission and a design-build entity to furnish: architecture, engineering, land surveying, public art or interpretive exhibits, and related services, as required; and the labor, materials, equipment, and other construction services for the project. See Illinois Compiled Statutes 65 ILCS 5/11-135.5-7
  • Design-build entity: means any individual, sole proprietorship, firm, partnership, joint venture, corporation, professional corporation, or other entity that proposes to design and construct any public project under this Division. See Illinois Compiled Statutes 65 ILCS 5/11-135.5-7
  • Proposal: means the offer to enter into a design-build contract as submitted by a design-build entity in accordance with this Division. See Illinois Compiled Statutes 65 ILCS 5/11-135.5-7
  • Request for proposal: means the document used by the commission to solicit proposals for a design-build contract. See Illinois Compiled Statutes 65 ILCS 5/11-135.5-7
  • Scope and performance criteria: means the requirements for the commission project, including, but not limited to, the intended usage, capacity, size, scope, quality and performance standards, life-cycle costs, and other programmatic criteria that are expressed in performance-oriented and quantifiable specifications and drawings that can be reasonably inferred and are suited to allow a design-build entity to develop a proposal. See Illinois Compiled Statutes 65 ILCS 5/11-135.5-7

     The commission shall include the following criteria in every Phase I evaluation of design-build entities: (i) experience of personnel; (ii) successful experience with similar project types; (iii) financial capability; (iv) timeliness of past performance; (v) experience with similarly sized projects; (vi) successful reference checks of the firm; and (vii) commitment to assign personnel for the duration of the project and qualifications of the entity’s consultants.
     The commission may include any additional relevant criteria in Phase I that it deems necessary for a proper qualification review. The commission may not consider any design-build entity for evaluation or award if the entity has any pecuniary interest in the project or has other relationships or circumstances, including, but not limited to, long-term leasehold, mutual performance, or development contracts with the commission, that may give the design-build entity a financial or tangible advantage over other design-build entities in the preparation, evaluation, or performance of the design-build contract or that create the appearance of impropriety.
     Upon completion of the qualifications evaluation, the commission shall create a shortlist of the most highly qualified design-build entities. The commission, in its discretion, is not required to shortlist the maximum number of entities as identified for Phase II evaluation, provided that no less than 2 design-build entities nor more than 6 are selected to submit Phase II proposals. The commission shall notify the entities selected for the shortlist in writing. This notification shall commence the period for the preparation of the Phase II technical and cost evaluations. The commission must allow sufficient time for the shortlist entities to prepare their Phase II submittals considering the scope and detail requested by the commission.
     (c) The commission shall include in the request for proposal the evaluating factors to be used in the technical and cost submission components of Phase II. Each request for proposal shall establish, for both the technical and cost submission components of Phase II, the relative importance assigned to each evaluation factor and subfactor, including any weighting of criteria to be employed by the commission. The commission must maintain a record of the evaluation scoring to be disclosed in event of a protest regarding the solicitation.
     The commission shall include the following criteria in every Phase II technical evaluation of design-build entities: (i) compliance with objectives of the project; (ii) compliance of proposed services to the request for proposal requirements; (iii) quality of products or materials proposed; (iv) quality of design parameters; (v) design concepts; (vi) innovation in meeting the scope and performance criteria; and (vii) constructability of the proposed project. The commission may include any additional relevant technical evaluation factors it deems necessary for proper selection.
     The commission shall include the following criteria in every Phase II cost evaluation: the total project cost; the construction costs; and the time of completion. The commission may include any additional relevant technical evaluation factors it deems necessary for proper selection. The total project cost criteria weighting factor shall not exceed 30%.
     The commission shall directly employ or retain a licensed design professional or a public art designer to evaluate the technical and cost submissions to determine if the technical submissions are in accordance with generally accepted industry standards.
     Upon completion of the technical submissions and cost submissions evaluation, the commission may award the design-build contract to the highest overall ranked entity.