The order of the commission must define the area of the common source of supply or portion thereof to be included within the unit area and prescribe with reasonable detail the plan of unitization applicable thereto.

Terms Used In North Dakota Code 38-08-09.4

  • Contract: A legal written agreement that becomes binding when signed.
  • Dependent: A person dependent for support upon another.
  • Equitable: Pertaining to civil suits in "equity" rather than in "law." In English legal history, the courts of "law" could order the payment of damages and could afford no other remedy. See damages. A separate court of "equity" could order someone to do something or to cease to do something. See, e.g., injunction. In American jurisprudence, the federal courts have both legal and equitable power, but the distinction is still an important one. For example, a trial by jury is normally available in "law" cases but not in "equity" cases. Source: U.S. Courts
  • Evidence: Information presented in testimony or in documents that is used to persuade the fact finder (judge or jury) to decide the case for one side or the other.
  • Lease: A contract transferring the use of property or occupancy of land, space, structures, or equipment in consideration of a payment (e.g., rent). Source: OCC
  • Remainder: An interest in property that takes effect in the future at a specified time or after the occurrence of some event, such as the death of a life tenant.

Each unit and unit area must be limited to all or a portion of a single common source of supply.

A unit may be created to embrace less than the whole of a common source of supply only where it is shown by the evidence that the area to be so included within the unit area is of such size and shape as may be reasonably required for the successful and efficient conduct of the unitized method or methods of operation for which the unit is created, and that the conduct thereof will have no material adverse effect upon the remainder of such common source of supply.

The plan of unitization for each such unit and unit area must be one suited to the needs and requirements of the particular unit dependent upon the facts and conditions found to exist with respect thereto. In addition to such other terms, provisions, conditions, and requirements found by the commission to be reasonably necessary or proper to effectuate or accomplish the purposes of sections 38-08-09.1 through 38-08-09.16, and subject to the further requirements hereof, each such plan of unitization must contain fair, reasonable, and equitable provisions for:

1.    The efficient unitized management or control of the further development and operation of the unit area for the recovery of oil and gas from the common source of supply affected. Under such a plan, the actual operations within the unit area may be carried on in whole or in part by the unit itself, or by one or more of the lessees within the unit area as unit operator subject to the supervision and direction of the unit, dependent upon what is most beneficial or expedient. The designation of the unit operator must be by a vote of the working interest owners in the unit in a manner provided by the plan of unitization and not by the commission, and the unit-operating agreement must contain a provision that the owners of a simple majority of the working interest in the unit area may vote to change the unit operator.

2.    The division of interest or formula for the apportionment and allocation of the unit production, among and to the several separately owned tracts within the unit area such as will reasonably permit persons otherwise entitled to share in or benefit by the production from such separately owned tracts to produce or receive, in lieu thereof, their fair, equitable, and reasonable share of the unit production or other benefits thereof. A separately owned tract’s fair, equitable, and reasonable share of the unit production must be measured by the value of each such tract for oil and gas purposes and its contributing value to the unit in relation to like values of other tracts in the unit, taking into account acreage [hectarage], the quantity of oil and gas recoverable therefrom, location on structure, its probable productivity of oil and gas in the absence    of unit operations, the burden of operation to which the tract will or is likely to be subjected, or so many of said factors, or such other pertinent engineering, geological, or operating factors, as may be reasonably susceptible of determination. Unit production as that term is used in sections 38-08-09.1 through 38-08-09.16 means and includes all oil and gas produced from a unit area from and after the effective date of the order of the commission creating the unit regardless of the well or tract within the unit area from which the same is produced.

3.    The manner in which the unit and the further development and operation of the unit area shall or may be financed and the basis, terms, and conditions on which the cost and expense thereof shall be apportioned among and assessed against the tracts and interests made chargeable therewith, including a detailed accounting procedure governing all charges and credits incident to such operations. Upon and subject to such terms and conditions as to time and legal rate of interest as may be fair to all concerned, reasonable provision must be made in the plan of unitization for carrying or otherwise financing owners who are unable to promptly meet their financial obligations in connection with the unit and, in addition to the unit expense assessed against each tract and chargeable to each owner, the recovery of a risk penalty from each owner electing not to participate in the unit expense. The recovery of the risk penalty is as follows:

a.    If the nonparticipating owner’s interest in the unit is derived from a lease or other contract for development, the risk penalty is two hundred percent of the nonparticipating owner’s share of the unit expense and may be recovered out of, and only out of, production from the unit, exclusive of any royalty or overriding royalty.

b.    If the nonparticipating owner’s interest in the unit is not subject to a lease or other contract for development, the penalty is fifty percent of the nonparticipating owner’s share of the unit expense and may be recovered out of production from the unit exclusive of any royalty provided for in section 38-08-09.13.

c.    The owner paying for the nonparticipating owner’s share of the unit expense may recover from the nonparticipating owner a risk penalty for the risk involved in the unit expense only if the paying owner has made an unsuccessful, good-faith attempt to have the unleased nonparticipating owner execute a lease or to have the leased nonparticipating owner join in and participate in the risk of the unit expense. Before a risk penalty may be imposed, the paying owner must notify the nonparticipating owner with proof of service that the paying owner intends to impose a risk penalty and that the nonparticipating owner may object to the risk penalty by either responding in opposition to the petition for a risk penalty or if no such petition has been filed, by filing an application or request for hearing with the industrial commission.

4.    The procedure and basis upon which wells, equipment, and other properties of the several lessees within the unit area are to be taken over and used for unit operations, including the method of arriving at the compensation therefor, or of otherwise proportionately equalizing or adjusting the investment of the several lessees in the project as of the effective date of unit operation.

5.    The creation of an operating committee to have general overall management and control of the unit and the conduct of its business and affairs and the operations carried on by it, together with the creation or designation of such other subcommittees, boards, or officers to function under authority of the operating committee as may be necessary, proper, or convenient in the efficient management of the unit, defining the powers and duties of all such committees, boards, or officers and prescribing their tenure and time and method for their selection.

6.    The time when the plan of unitization shall become and be effective.

7.    The time when and conditions under which and the method by which the unit must or may be dissolved and its affairs wound up; however, the unit may be dissolved ten years after the unit agreement becomes effective upon a petition to the commission by the royalty owners who are credited with at least the percentage of interest of the    royalty production and proceeds thereof required to ratify the unit agreement on the date the unit agreement was initially approved by the commission, and a subsequent hearing and order by the commission. The commission may not dissolve any unit if the dissolution would be likely to result in waste or the violation of the correlative rights of any owner. This provision does not limit or restrict any other authority which the commission has.