(a) Local distribution

Any facility receiving natural gas from an Alaska natural gas transportation project for delivery to consumers within the State—

(1) shall be deemed to be a local distribution facility within the meaning of section 1(b) of the Natural Gas Act (15 U.S.C. 717(b)); and

(2) shall not be subject to the jurisdiction of the Commission.

(b) Additional pipelines

Terms Used In 15 USC 720f

  • Jurisdiction: (1) The legal authority of a court to hear and decide a case. Concurrent jurisdiction exists when two courts have simultaneous responsibility for the same case. (2) The geographic area over which the court has authority to decide cases.
  • State: means a State, the District of Columbia, the Commonwealth of Puerto Rico, or any other territory or possession of the United States. See 1 USC 7

Except as provided in section 720a(d) of this title, nothing in this chapter shall preclude or otherwise affect a future natural gas pipeline that may be constructed to deliver natural gas to Fairbanks, Anchorage, Matanuska-Susitna Valley, or the Kenai peninsula or Valdez or any other site in the State for consumption within or distribution outside the State.

(c) Rate coordination

(1) In general

In accordance with the Natural Gas Act [15 U.S.C. 717 et seq.], the Commission shall establish rates for the transportation of natural gas on any Alaska natural gas transportation project.

(2) Consultation

In carrying out paragraph (1), the Commission, in accordance with section 17(b) of the Natural Gas Act (15 U.S.C. 717p(b)), shall consult with the State regarding rates (including rate settlements) applicable to natural gas transported on and delivered from the Alaska natural gas transportation project for use within the State.