Each plan shall contain descriptions, including appropriate maps and cross section drawings of the proposed disposal methods and sites for placing underground development waste and excess spoil generated at surface areas affected by surface operations and facilities, according to 30 CFR 817.71 through 817.74. Each plan shall describe the geotechnical investigation, design, construction, operation, maintenance and removal, if appropriate, of the structures and be prepared according to 30 CFR 780.35.

Ask a business law question, get an answer ASAP!
Thousands of highly rated, verified business lawyers.
Click here to chat with a lawyer about your rights.

[79 FR 76230, Dec. 22, 2014, as amended at 81 FR 93355, Dec. 20, 2016; 82 FR 54958, Nov. 17, 2017]