California Public Utilities Code 2812.5 – Upon application of a private energy producer, and after notice to …
Upon application of a private energy producer, and after notice to any affected public utility and hearing thereon, the commission shall authorize such producer to construct an interconnection for the purpose of transmitting electricity, if the commission finds:
(1) That no uncompensated burden will be placed upon the utility or utilities furnishing the transmission service.
Terms Used In California Public Utilities Code 2812.5
- Commission: means the Public Utilities Commission created by §. See California Public Utilities Code 20
- Corporation: A legal entity owned by the holders of shares of stock that have been issued, and that can own, receive, and transfer property, and carry on business in its own name.
(2) That furnishing the transmission service will not result in any added costs or any other adverse consequences for the customers of the electrical corporation.
(3) That the facilities proposed in the application will be used to transmit power from other than a conventional power source for generating electrical power.
The commission shall prescribe such reasonable terms, conditions, and requirements as it deems appropriate.
(Added by Stats. 1976, Ch. 915.)