Indiana Code 13-18-27-17. Trained individual to make or supervise making of determination concerning construction plan
Current as of: 2023 | Check for updates
|
Other versions
Sec. 17. (a) This section does not apply to an individual employed on July 1, 2019, to review and make conclusive determinations concerning construction plans submitted to an MS4 community.
(1) a trained individual; or
(b) An individual who reviews and makes a conclusive determination concerning a construction plan submitted to an MS4 community must be:
Terms Used In Indiana Code 13-18-27-17
- construction plan: means a written plan that:
Indiana Code 13-18-27-3
- trained individual: means an individual who is trained and experienced in the principles of storm water management, including erosion and sediment control, as demonstrated by:
Indiana Code 13-18-27-13
(2) an individual working under the direct supervision of a trained individual.
As added by P.L.248-2019, SEC.14.