1.    An application for a certificate must be in such form as the commission may prescribe, containing the following information:

Terms Used In North Dakota Code 49-22-08

  • Amendment: A proposal to alter the text of a pending bill or other measure by striking out some of it, by inserting new language, or both. Before an amendment becomes part of the measure, thelegislature must agree to it.
  • Evidence: Information presented in testimony or in documents that is used to persuade the fact finder (judge or jury) to decide the case for one side or the other.
  • following: when used by way of reference to a chapter or other part of a statute means the next preceding or next following chapter or other part. See North Dakota Code 1-01-49
  • Jurisdiction: (1) The legal authority of a court to hear and decide a case. Concurrent jurisdiction exists when two courts have simultaneous responsibility for the same case. (2) The geographic area over which the court has authority to decide cases.
  • Person: means an individual, organization, government, political subdivision, or government agency or instrumentality. See North Dakota Code 1-01-49
  • State: when applied to the different parts of the United States, includes the District of Columbia and the territories. See North Dakota Code 1-01-49

a.    A description of the size and type of facility.

b.    A summary of any studies which have been made of the environmental impact of the facility.

c.    A statement explaining the need for the facility.

d. An identification of the location of the preferred site for any electric energy conversion facility.

e.    An identification of the location of the preferred corridor for any electric transmission facility.

f.    A description of the merits and detriments of any location identified and a comprehensive analysis with supporting data showing the reasons why the preferred location is best suited for the facility.

g.    A description of mitigative measures that will be taken to minimize all foreseen adverse impacts resulting from the location, construction, and operation of the proposed facility.

h. An evaluation of the proposed site or corridor with regard to the applicable considerations set out in section 49-22-09 and the criteria established pursuant to section 49-22-05.1.

i.    Such other information as the applicant may consider relevant or the commission may require.

2.    After determining that the application is complete, the commission shall serve a notice of filing of the application on such persons and agencies that the commission may deem appropriate and shall publish a notice of filing of the application in the official newspaper of each county in which any portion of the site or corridor is proposed to be located.

    3.    A copy of the application shall be furnished to any person or agency, upon request to the commission within thirty days of either service or publication of the notice of filing.

4.    Within thirty days following service of the notice of filing of a complete application by the commission, the applicant shall provide a copy of the commission’s notice of filing of the application by first-class mail to the owner of record of any land located within the requested site or corridor. For purposes of this subsection, the owner of record means the owner identified by the county treasurer to receive the real estate tax statement.

5.    An application for an amendment of a certificate shall be in such form and contain such information as the commission shall prescribe.

6.    The commission may designate a site or corridor for a proposed facility following the study and hearings provided for in this chapter. Any designation shall be made in accordance with the evidence presented at the hearings, an evaluation of the information provided in the application, the criteria established pursuant to section 49-22-05.1, and the considerations set out in section 49-22-09 in a finding with reasons for the designation, and shall be made in a timely manner no later than six months after the filing of a completed application for a certificate of site compatibility or no later than three months after the filing of a completed application for a certificate of corridor compatibility. The time for designation of a site or corridor may be extended by the commission for just cause. The failure of the commission to act within the time limits provided in this section shall not operate to divest the commission of jurisdiction in any certification proceeding. The commission shall indicate the reasons for any refusal of designation. Upon designation of a site or corridor, the commission shall issue a certificate of site compatibility or a certificate of corridor compatibility with such terms, conditions, or modifications deemed necessary. The commission may not condition the issuance of a certificate or permit on the applicant providing a mitigation payment assessed or requested by another state agency or entity to offset a negative impact on wildlife habitat.